June 06 2023

MCEA Phase 1 – Problem and Opportunity

Notice of Study of Commencement

Identify the problem and opportunities.

June 21 2023

MCEA Phase 2 – Alternative Solutions

Public Information Centre (online consultation). 

Identify and evaluate alternative solutions

December 01 2023

MCEA Phase 3 – Alternative Design Concepts

Identify and evaluate Design Concepts for the preferred solution

PIC 2 – Winter 2023

March 01 2024

MCEA Phase 4 – Master Plan - Environmental Study Report

Prepare a Master Plan Environmental Study Report and post online for public review and comment. Early Winter 2024

EA Completion –Winter/Spring 2024

May 01 2024

MCEA Phase 5 - Implementation

Construction Commencement – Summer 2025